Update: Route 28 Water Improvements Project

Town of Derry Seal

The mainline water main and services to the edge of the right-of-way are fully installed and pressure tested on all roads.  Base course paving is complete on all roads and driveways. Loam and seed and cleanup activities are almost complete. 

Water service is now available to abutting properties. Residents will be notified that they may now connect public water.

The water connection on Gervaise Drive and installation of the water services on private property and into basements for 12 MtBE properties will be completed in September 2017. Residents of the Woodlands neighborhood will be notified when the Town will transition their water system from their wells to municipal water.

Substantial completion is anticipated in October 2017.